Progress over the Years
Over the years we have made tremendous progress, from mere bushes to a very nice looking school campus. Truly amazing!!
February 1st 2006
Ground-breaking for the construction of the first classroom block – 5 classrooms, 2 offices and a staffroom
December 18, 2006
Registration of pupils started.
February 5, 2007
School opened with 261 pupils, Kindergarten through 5th Grade.
May 1st, 2007
Official opening of the school by Bishop Christopher Kakooza, auxiliary bishop of Kampala Archdiocese. This occasion also marked the centenary celebrations of St. Joseph sub-parish church Busukuma and the official opening of the new church which was built to commemorate the Jubilee year 2000.
November 2007
Construction of the second classroom block started – 4 classrooms.
February 2008
6th Grade was added, bringing the total enrollment to 330 pupils.
December 2008
Completion of second classroom block.
February 2009: 7th Grade was added, bringing the total enrollment to 350.
Completion of second classroom block.
February 2009: Construction of teachers’ quarters.
Completion of second classroom block.
October 2008: Dentals Services started but were done in the computer lab.
Completion of second classroom block.
December 2009: Graduation of the P.7 Pioneer class. (pictures)
Completion of second classroom block.
October 2009: Construction of the first dormitory and a dental clinic started.
Completion of second classroom block.
April 2010: Completion of the dormitory and dental clinic. Dentals services were transferred to the dental clinic.
Completion of second classroom block.
October 2010: Construction of a Water Well (St. Martin’s Water Well).
Completion of second classroom block.
November 2011 Construction of the third classroom block for the Kindergarten section, Library, recreation center and offices
Completion of second classroom block.
2012: Continuation of the construction of the third classroom block.
Completion of second classroom block.
February 2013: Completion of the third classroom block. (pictures)
Completion of second classroom block.
June 2013: Visit by Oscar Valenzuela and Nick Sherg from Yorba Linda
Completion of second classroom block.
Boys Dormitories were added in 2014 and completed 2015
Completion of second classroom block.
Modern Bathrooms added 2014/2015
Completion of second classroom block.
Toilets were added 2015
Completion of second classroom block.
Construction of a Multipurpose Hall started in October 2015 and completed in February 2017.
Completion of second classroom block.
Paving of the compound started in October 2016 through February 2017
Completion of second classroom block.
Construction of Mary Jo’s Kindergarten started in January 2017.
Completion of second classroom block.